yuzhno-sakhalinsk, drilled piles cfa (Continuous flight auger) technology

deep foundation, yuzhno-sakhalinsk, sheet piles driving with pre-driling and diesel hammer final driving

bridge foundation, river srednaya, Mitsulevka, pipes driving with hole cleaning diam 610mm, depht 26m & 31m

BRIDGE, river komisarovka

railway BRIDGE, mitsylevka

yuzhno-sakhalinsk.  foundation for office building. Borehole pilling with the use of casing pipes, diam 426mm, depth 4,6m,   296 each

ilinskoe. foundation for water stock. concrete sectional piles 40x40, lenght 21m=10+11. q-ty 354each

uglegorsk. bridge foundation. concrete sectional piles 40x40, lenght 20m=9m+11m

ilinskoe. dynamic tests of field by piles. foundation for water stock. concrete sectional piles 40x40, lenght 24m=12+12

ilinskoe. bridge pile foundation. concrete sectional piles 40x40, lenght 19m=8m+11m,   64 each

yuzhno-sakhalinsk. Static and dynamic tests of field by piles. foundation for corn stock. concrete piles 30x30, lenght 5m-10m,   33 each

Taranay, Anivskiy region. foundation for pig farm. concrete piles 30x30, lenght 5m-11m,     2549 each

Yuzhno-sakhalinsk, foundation for 10 levels building,  bored piles Depth 16м,  Diam 426mm, 34 each.

Yuzhno-sakhalinsk, foundation for gas pipeline,  pipes driving, cleaning holes,  diam 1020mm, lenght 11 m,  20 each

Yuzhno-sakhalinsk, foundation for chimney,  pipes driving, cleaning holes,  diam 700mm, lenght 8 m,  7 each

Yuzhno-sakhalinsk, foundation for 10 levels building,  pre-drilling before sheet pile driving.  diam 500mm, depth 12m,   

poronaisk, coal boiler house, foundation for  heating main, concrite piles 30x30cm, lenght 9 m,  84 each

makarov region, Vostochnoe vilage,  bearing foundation for High-voltage line, pipe piles with fitting 325 x 12 x 9, 2each

yuzhno-sakhalinsk, appartment buildings, concrete piles 30x30, lenght 8 m, 275 each 

 Yuzhno-sakhalinsk.   power station, second phase, drilling 500mm with casing pipe driving diam 426mm, lenght 6,8m, 107 each

 NEW equipment!!! yuzhno-sakhalinsk, warehouse store,  dynamic method of field testing by piles, concrete piles 30x30, lenght 7 and 12 m, 34 each

dalnee, appartment building, concrete piles 30x30, lenght 9 m, 46 each

mgachi, children garden, drilling 500mm with casing pipe driving diam426mm, lengt 6,8m, 110 each

novo-troitskoe, appartment building, concrete piles 30x30, lenght 8m, 108 each

dalnee, appartment building, concrete piles 30x30, lenght 9 & 11m, 68 each

 Yuzhno-sakhalinsk.   power station, drilling 500mm with casing pipe driving diam 426mm, lenght 6,8m

 NEW equipment!!! Timovskoe.   children garden 200 rerson,  dynamic method of field testing by piles, concrete piles 30x30,  25x25, lenght 7 and 6 m, 555 each

 Shakhtersk. road construction, water tube,  concrete  piles, dynamic method of field testing by piles, 35x35, lenght 8 m, 69 each

 new equipment!!! Sovetskoe. Bridge bearing, concrete component piles, 40x40, lenght 9+8 m, vertical and tilt piles

 taranay. dinamic method of field testing by piles.  pig-breeding farm.30x30, lenght 8,5 m, total q-ty 192 each

 Kholmsk,  garage with office. concrete piles 30x30, lenght 4,5 m, 98 each

 Yuzhno-Sakhalinsk,  warehouse store. concrete piles 30x30, lenght 8,9,10 m, 303 each 

 Aniva region, Zolotoribnoe vilage. Vegetable store 3500 ton. concrete piles 30x30, lenght 7-8 m, 48 each

 Kholmsk.  Reconstruction of  water storage. Installation of PIPES lenght 40 ft, diam 6,7 inch (12m/170mm). Drilling debth 46ft, diam 11,8inch (14m/300mm). 12 each

Yuzhno-Sakhalinsk. Reconstruction of  City ZOO. Installation of timber piles lenght 12 m. with predrilling. 11 each


Taranay village. Pig-breeding farm for 12000 heads. Concrete piles driving. 30x30, 4,8,10,11m.


Yuzhno-Sakhalinsk. Green Palace, H-piles driving with predrilling. 30x30, 12m, 12 each


Yuzhno-Sakhalinsk. Concrete plant. Concrete piles driving 30х30, 8m, 25 each


Gornozavodsk, footbridge. Concrete piles driving with predrilling. 40x40, 12m


Aniva. Living house. Concrete piles driving. 30x30, 7m. 108 each