DRILLING & DRIVING  on the one machine

Appearance of DRILLING + PILE DRIVING MACHINE 

To start working and avoid downtime it is necessary to have:

-A ground with a firm footing (The car weighs 22 tons. When the boom is turned, it puts pressure upon shoes that can slump through the ground and take an unstable position) It may causes tumbling of the machine or plumb line deviation. In that case, the soft ground is covered with rock or mats

- A pile field marked by landman 



working steps for drilling

1-st STEP

Taking working place. The machine is approached to the place of drilling, the bracing jacks are lowered, the drilling steel is fixed under the drilling site

 
 

2-nd STEP

hole drilling 

 

 

3-rd STEP 
Drilling rig relocation. The boom is downed. The machine is moved to the next well
.
 
 

working steps for DRIVING with PREDRILIING

 1. The machine is approached to the place of drilling, the bracing jacks are lowered, the drilling steel is fixed under the drilling site

 
 

2. DRILLING of lider hole

 

 

 

 

 

Pile SUPPLYING by excavator

crane, wheel loader are acceptable for the pile supplying too.

 
 
 

3. Pile LIFTING

4. Pile INSTALATION to leader hole


5.  Halmet with piles head CONNECTING

6. Pile DRIVING

7.  Drilling rig relocation. The boom is downed. The machine is moved to the next well 

***  lifting height of the hummer is 315 inches, that’s why the min length of the pile is 315 inches 


***  the platform can be rotated by 180 degrees and it`s longitudinal motion is 3150 inches, so it`s possible to drill in pile clusters without relocation


***  to increase output drilling process can be chanced